Greenfield Data Center – Phase 1

New 20MW data center facility with redundant power, advanced cooling systems, and raised-floor server rooms.

ACTIVE

Statement of Work

Greenfield Data Center – Phase 1 - Statement of Work.pdf

application/pdf

$55,000,000.00PROCESSED

Extracted Scope Items (8)

Site & Civil

Grading, stormwater management, access roads, and security fencing.

Site Work

Building Shell

Pre-engineered metal building with concrete tilt-up panels for server halls.

Structural

Electrical – Utility & Switchgear

Dual utility feeds, 20MW switchgear, transformers, and ATS systems.

Electrical

Backup Power

N+1 diesel generator farm with 48-hour fuel storage.

Electrical

Cooling Systems

Chilled water plant with economizer mode, CRAHs, and hot/cold aisle containment.

MEP

Raised Floor & Cabling

24-inch raised floor system with underfloor cable management for server rooms.

Interior

Fire Suppression

Pre-action dry pipe and clean agent (Novec 1230) suppression for server halls.

Fire Protection

Security & BMS

Mantraps, biometric access, CCTV, and building management system integration.

Security

Scope Drifts

Unforeseen conditions impacting Backup Power
HIGHNEEDS REVIEW

During execution of Backup Power, unforeseen site conditions were discovered that require additional engineering and remediation work not covered in the original scope.

Scope IncreaseFrom: Budget Review MeetingConfidence: 86%Scope: Backup Power$1,020,000
Additional Site & Civil work requested by owner
HIGHACCEPTED

Owner has requested additional Site & Civil scope beyond the original SOW. This was discussed during a recent progress meeting and would require a change order.

Scope IncreaseFrom: Subcontractor CoordinationConfidence: 90%Scope: Site & Civil$675,000
Material upgrade for Building Shell
MEDIUMNEEDS REVIEW

Architect specified upgraded materials for Building Shell that differ from the original SOW spec. This change increases material costs but was presented as a preference, not a requirement.

Scope IncreaseFrom: RFI Review SessionConfidence: 72%Scope: Building Shell$640,000
Raised Floor & Cabling redesign due to code update
HIGHACCEPTED

Recent building code update requires redesign of Raised Floor & Cabling. The new requirements were published after the original SOW was finalized.

Scope IncreaseFrom: RFI Review SessionConfidence: 72%Scope: Raised Floor & Cabling$350,000
Value engineering – Cooling Systems reduction
LOWDISMISSED

Team proposed a value engineering option to reduce Cooling Systems costs by substituting equivalent materials and simplifying the installation approach.

Scope ReductionFrom: Owner/Architect/Contractor MeetingConfidence: 64%Scope: Cooling Systems$600,000
Electrical – Utility & Switchgear schedule acceleration
MEDIUMNEEDS REVIEW

Client requested that the Electrical – Utility & Switchgear phase be completed 2 weeks ahead of the original schedule. This would require overtime labor and expedited material deliveries.

Timeline ChangeFrom: Weekly Progress SyncConfidence: 86%Scope: Electrical – Utility & Switchgear$600,000

Meetings

Past Meetings

Budget Review Meeting

3/25/2026

PROCESSED

Change Order Discussion

3/19/2026

PROCESSED

Subcontractor Coordination

3/14/2026

PROCESSED

RFI Review Session

3/11/2026

PROCESSED

Owner/Architect/Contractor Meeting

3/6/2026

PROCESSED

Weekly Progress Sync

3/1/2026

PROCESSED