Harbor District Parking Garage

6-level precast concrete parking structure with 850 spaces, EV charging stations, and rooftop solar array.

ACTIVE

Statement of Work

Harbor District Parking Garage - Statement of Work.pdf

application/pdf

$18,200,000.00PROCESSED

Extracted Scope Items (6)

Foundations & Piling

Deep foundation system with driven piles due to proximity to waterfront.

Structural

Precast Structure

Precast double-tee beams, columns, and spandrels for 6-level garage.

Structural

MEP & Fire Protection

Ventilation, lighting, fire sprinklers, and electrical distribution.

MEP

EV Charging Infrastructure

Installation of 120 Level 2 chargers and 20 DC fast chargers with electrical backbone.

Electrical

Rooftop Solar Array

500 kW solar canopy system on top deck with inverters and grid tie-in.

Electrical

Wayfinding & Striping

Pavement markings, signage, pedestrian safety features, and access control gates.

Finishes

Scope Drifts

MEP & Fire Protection schedule acceleration
MEDIUMNEEDS REVIEW

Client requested that the MEP & Fire Protection phase be completed 2 weeks ahead of the original schedule. This would require overtime labor and expedited material deliveries.

Timeline ChangeFrom: Owner/Architect/Contractor MeetingConfidence: 69%Scope: MEP & Fire Protection$140,000
Unforeseen conditions impacting EV Charging Infrastructure
HIGHNEEDS REVIEW

During execution of EV Charging Infrastructure, unforeseen site conditions were discovered that require additional engineering and remediation work not covered in the original scope.

Scope IncreaseFrom: Owner/Architect/Contractor MeetingConfidence: 77%Scope: EV Charging Infrastructure$192,000
Additional Foundations & Piling work requested by owner
HIGHNEEDS REVIEW

Owner has requested additional Foundations & Piling scope beyond the original SOW. This was discussed during a recent progress meeting and would require a change order.

Scope IncreaseFrom: Weekly Progress SyncConfidence: 82%Scope: Foundations & Piling$510,000
Material upgrade for Precast Structure
MEDIUMACCEPTED

Architect specified upgraded materials for Precast Structure that differ from the original SOW spec. This change increases material costs but was presented as a preference, not a requirement.

Scope IncreaseFrom: Weekly Progress SyncConfidence: 91%Scope: Precast Structure$656,000

Meetings

Past Meetings

Change Order Discussion

3/24/2026

PROCESSED

Subcontractor Coordination

3/16/2026

PROCESSED

RFI Review Session

3/12/2026

PROCESSED

Owner/Architect/Contractor Meeting

3/6/2026

PROCESSED

Weekly Progress Sync

3/2/2026

PROCESSED