Riverdale Mixed-Use Complex
12-story mixed-use development with ground-floor retail and 180 residential units. Includes underground parking garage.
Statement of Work
Riverdale Mixed-Use Complex - Statement of Work.pdf
application/pdf
Extracted Scope Items (8)
Site Work & Excavation
Demolition of existing structures, grading, and excavation for foundation and underground parking.
Structural – Foundation & Parking
Reinforced concrete foundation, underground parking structure (2 levels, 220 spaces).
Structural – Superstructure
Steel and concrete superstructure for 12 stories including elevator shafts and stairwells.
Building Envelope
Curtain wall system, window installation, waterproofing, and insulation.
MEP Systems
Mechanical, electrical, and plumbing rough-in and finish for all 12 floors.
Interior Fit-Out – Residential
Finishes, cabinetry, fixtures, and appliances for 180 units.
Interior Fit-Out – Retail
White-box delivery for 6 ground-floor retail bays totaling 18,000 SF.
Landscaping & Amenities
Rooftop terrace, courtyard, landscaping, and irrigation systems.
Scope Drifts
Recent building code update requires redesign of Interior Fit-Out – Residential. The new requirements were published after the original SOW was finalized.
Client requested that the Structural – Superstructure phase be completed 2 weeks ahead of the original schedule. This would require overtime labor and expedited material deliveries.
Architect specified upgraded materials for Structural – Foundation & Parking that differ from the original SOW spec. This change increases material costs but was presented as a preference, not a requirement.
Owner has requested additional Site Work & Excavation scope beyond the original SOW. This was discussed during a recent progress meeting and would require a change order.
Team proposed a value engineering option to reduce MEP Systems costs by substituting equivalent materials and simplifying the installation approach.
During execution of Building Envelope, unforeseen site conditions were discovered that require additional engineering and remediation work not covered in the original scope.
Owner decided to defer Interior Fit-Out – Retail work to a future phase, removing it from the current contract scope.
Meetings
Paste or upload a transcript to analyze for scope drift
Upload an audio recording to transcribe and analyze
Record live audio and transcribe in real-time
Past Meetings
Budget Review Meeting
3/23/2026
Change Order Discussion
3/20/2026
Subcontractor Coordination
3/15/2026
RFI Review Session
3/10/2026
Owner/Architect/Contractor Meeting
3/4/2026
Weekly Progress Sync
3/2/2026