FerrisScope Drift Radar
← Back to Projects

Riverdale Mixed-Use Complex

12-story mixed-use development with ground-floor retail and 180 residential units. Includes underground parking garage.

ACTIVE

Statement of Work

Riverdale Mixed-Use Complex - Statement of Work.pdf

application/pdf

$42,500,000.00PROCESSED

Extracted Scope Items (8)

Site Work & Excavation

Demolition of existing structures, grading, and excavation for foundation and underground parking.

Site Work

Structural – Foundation & Parking

Reinforced concrete foundation, underground parking structure (2 levels, 220 spaces).

Structural

Structural – Superstructure

Steel and concrete superstructure for 12 stories including elevator shafts and stairwells.

Structural

Building Envelope

Curtain wall system, window installation, waterproofing, and insulation.

Envelope

MEP Systems

Mechanical, electrical, and plumbing rough-in and finish for all 12 floors.

MEP

Interior Fit-Out – Residential

Finishes, cabinetry, fixtures, and appliances for 180 units.

Interior

Interior Fit-Out – Retail

White-box delivery for 6 ground-floor retail bays totaling 18,000 SF.

Interior

Landscaping & Amenities

Rooftop terrace, courtyard, landscaping, and irrigation systems.

Exterior

Scope Drifts

Interior Fit-Out – Residential redesign due to code update
HIGHNEEDS REVIEW

Recent building code update requires redesign of Interior Fit-Out – Residential. The new requirements were published after the original SOW was finalized.

Scope IncreaseFrom: Budget Review MeetingConfidence: 63%Scope: Interior Fit-Out – Residential$520,000
Structural – Superstructure schedule acceleration
MEDIUMDISMISSED

Client requested that the Structural – Superstructure phase be completed 2 weeks ahead of the original schedule. This would require overtime labor and expedited material deliveries.

Timeline ChangeFrom: Budget Review MeetingConfidence: 71%Scope: Structural – Superstructure$490,000
Material upgrade for Structural – Foundation & Parking
MEDIUMNEEDS REVIEW

Architect specified upgraded materials for Structural – Foundation & Parking that differ from the original SOW spec. This change increases material costs but was presented as a preference, not a requirement.

Scope IncreaseFrom: Change Order DiscussionConfidence: 94%Scope: Structural – Foundation & Parking$680,000
Additional Site Work & Excavation work requested by owner
HIGHNEEDS REVIEW

Owner has requested additional Site Work & Excavation scope beyond the original SOW. This was discussed during a recent progress meeting and would require a change order.

Scope IncreaseFrom: RFI Review SessionConfidence: 94%Scope: Site Work & Excavation$480,000
Value engineering – MEP Systems reduction
LOWNEEDS REVIEW

Team proposed a value engineering option to reduce MEP Systems costs by substituting equivalent materials and simplifying the installation approach.

Scope ReductionFrom: RFI Review SessionConfidence: 69%Scope: MEP Systems$456,000
Unforeseen conditions impacting Building Envelope
HIGHDISMISSED

During execution of Building Envelope, unforeseen site conditions were discovered that require additional engineering and remediation work not covered in the original scope.

Scope IncreaseFrom: Owner/Architect/Contractor MeetingConfidence: 85%Scope: Building Envelope$648,000
Owner deferred Interior Fit-Out – Retail to Phase 2
LOWNEEDS REVIEW

Owner decided to defer Interior Fit-Out – Retail work to a future phase, removing it from the current contract scope.

Scope ReductionFrom: Weekly Progress SyncConfidence: 77%Scope: Interior Fit-Out – Retail$180,000

Meetings

Past Meetings

Budget Review Meeting

3/23/2026

PROCESSED

Change Order Discussion

3/20/2026

PROCESSED

Subcontractor Coordination

3/15/2026

PROCESSED

RFI Review Session

3/10/2026

PROCESSED

Owner/Architect/Contractor Meeting

3/4/2026

PROCESSED

Weekly Progress Sync

3/2/2026

PROCESSED