FerrisScope Drift Radar
← Back to Projects

Hudson House

ACTIVE

Statement of Work

Hudson_Scope_of_Work_PDF.pdf

application/pdf

$12,000,000.00PROCESSED

Extracted Scope Items (7)

Mixed-Use Building Design and Construction

Design and build a six-story mixed-use building with ground-floor retail and residential levels above in Hoboken, NJ.

1.0 PROJECT DESCRIPTION

Structural System

Includes shallow foundation system, reinforced concrete slab, structural steel framing, composite metal deck, and lateral force-resisting system.

3.0 STRUCTURAL SCOPE

Civil Engineering Work

Tasks include site grading, stormwater management, connection to municipal utilities, and surface drainage systems.

4.0 CIVIL / SITE SCOPE

Architectural Design

Includes standard façade system, mechanical loads without atypical support, and systems designed within standard loading assumptions.

5.0 ARCHITECTURAL / PROGRAM REQUIREMENTS

Geotechnical Requirements

Relies on subsurface soils suitable for the project and no additional geotechnical investigations outside preliminary data.

6.0 GEOTECHNICAL CONSIDERATIONS

Construction Assumptions

Construction assumed to proceed linearly without phasing, using conventional methods, and no major revisions post-IFC documents.

7.0 CONSTRUCTION ASSUMPTIONS

Exclusions

Excludes deep foundation systems, major utility relocations, flood mitigation, and environmental remediation.

8.0 EXCLUSIONS

Scope Drifts

Drywall Replacement
MEDIUMNEEDS REVIEW

Discussion about replacing the entirety of the drywall suggests an addition to the scope.

Scope IncreaseFrom: Live CallConfidence: 85%Scope: Mixed-Use Building Design and Construction
Roof Lounge Addition
MEDIUMACCEPTED

Ownership has requested to make the roof more usable by adding a small lounge area, which was not part of the original scope.

Scope IncreaseFrom: Audio RecordingConfidence: 85%Scope: Architectural Design$230,000
Rooftop Lounge and Landscaping
HIGHACCEPTED

There is a proposal to activate the roof space with a lounge and landscaping, which requires additional structural considerations not included in the original scope.

Scope IncreaseFrom: Weekly MeetingConfidence: 90%Scope: Architectural Design$250,000
Utilities Conflict with Foundations
MEDIUMACCEPTED

The existing storm line location may interfere with planned building footings, requiring potential relocation or redesign of foundations.

Scope IncreaseFrom: Weekly MeetingConfidence: 80%Scope: Civil Engineering Work$30,000
Simplification of Steel Connections
MEDIUMACCEPTED

Field difficulties require redesign and coordination of structural steel connections, which goes beyond the linear construction methods assumed in the original scope.

Scope IncreaseFrom: Weekly MeetingConfidence: 70%Scope: Structural System$120,000

Meetings

Past Meetings

Live Call

3/28/2026

PROCESSED

Audio Recording

3/28/2026

PROCESSED

Weekly Meeting

3/24/2026

PROCESSED