Extracted Scope Items (7)

Mixed-Use Building Construction

Design and construction of a six-story mixed-use building including ground-floor retail and residential levels.

1.0 PROJECT DESCRIPTION

Structural System

Includes shallow foundations, reinforced concrete slab, structural steel framing, composite metal deck, and braced frames.

3.0 STRUCTURAL SCOPE

Civil and Site Work

Site grading, stormwater management, utility connections and surface drainage systems.

4.0 CIVIL / SITE SCOPE

Architectural Requirements

Standard façade system, standard mechanical loads, and no significant structural re-support is required.

5.0 ARCHITECTURAL / PROGRAM REQUIREMENTS

Geotechnical Considerations

Utilization of preliminary geotechnical information for foundation design, without additional investigation.

6.0 GEOTECHNICAL CONSIDERATIONS

Construction Assumptions

Linear construction process with conventional means and no major revisions planned.

7.0 CONSTRUCTION ASSUMPTIONS

Exclusions

Excludes deep foundation systems, retention systems beyond standard practice, below-grade structures, flood measures, and more.

8.0 EXCLUSIONS

Scope Drifts

Additional Drywall Installation
MEDIUMACCEPTED

During the meeting, it was discussed that additional drywall would be needed for the building, which represents a scope increase beyond the standard architectural requirements captured in the SOW.

Scope IncreaseFrom: WEekly meetingConfidence: 80%Scope: Architectural Requirements$100,000
Screening Mechanical Units on Roof
MEDIUMNEEDS REVIEW

Request to add screening for mechanical units on the roof that could increase the structural load.

Scope IncreaseFrom: Weekly MeetingConfidence: 80%Scope: Architectural Requirements
Utility Conflict and Foundation Adjustment
HIGHNEEDS REVIEW

The storm line location may conflict with footings, requiring potential foundation shifts or rerouting.

Scope IncreaseFrom: Weekly MeetingConfidence: 85%Scope: Civil and Site Work
Redesign of Steel Connections
MEDIUMNEEDS REVIEW

Proposed simplification of difficult field connections requiring redesign and coordination.

Timeline ChangeFrom: Weekly MeetingConfidence: 75%Scope: Structural System
Activation of Roof Space
HIGHACCEPTED

Introduction of a small lounge area with seating and landscaping on the roof, which was not included in the original project design.

Scope IncreaseFrom: Weekly MeetingConfidence: 90%Scope: Mixed-Use Building Construction$50,000